Production Schedule Adherence
The share of scheduled production completed as planned, in the planned sequence and quantity.
Definition
The share of scheduled production completed as planned, in the planned sequence and quantity.
Why it matters
Poor adherence breaks material plans, creates unplanned changeovers and quietly destroys promised customer dates.
Formula
Schedule Adherence = Units Produced As Scheduled / Units Scheduled x 100
Example
1,850 of 2,000 scheduled units built to plan gives 92.5% adherence.
How to interpret it
Below 90% usually points to material shortages, unrealistic capacity assumptions or frequent expedites.
How to improve it
Freeze the near-term schedule, verify material availability before release, and track and remove the top reasons for deviation.
Common mistakes
Counting total output rather than output that matched the schedule, which rewards building the easy orders.
Related KPIs
Frequently asked questions
- What is a realistic target?
- Many discrete manufacturers work toward 95% within a frozen horizon of one to two weeks.